PART 1
SITE PREPARATION
A. LOCATION AND LAYOUT
Figure 1. Barrier Gate Operator Layout.
NOTE
Figure 1 shows two different single gate installations. For location and layout details of Bi-Parting,
Bi-Parting Latch, Trap and Tandem gates, see Installation and Operation of Master/Slave Systems
for Series X1 Gate Operators, Document Number 6001376, Part 1.
1. Always install the gate operator on the inside of the fence line. NEVER install on the public
side of the fence.
2. All manual controls and activating devices should be mounted at least 6 feet away from the
gate to provide safety.
3. Allow enough clearance around the gate and the gate operator for installation and service.
INSTALLATION NOTES