Getting Started
P5205 Instruction Manual
7
Functional Check
To make a simple functional check of the P5205 probe, selec t a
source that supplies AC line voltage and use the following
procedure. This procedure verifies a majority of the circuitry within
the probe. For a complete performance verification, refe r to the
Performance Verification section starting on page 27.
1. Use the installation procedure starting on page 6 to connec t t he
output of the P5205 probe to a measurement instrument.
2. Connect the inputs, set the range, and perform the check as each
line of Table 1, below, indicates.
Table 1: Functional check
Input 1
(+ or --)
Input 2
(-- or +) Mode
Range
setting Check
Hot Ground or
Neutral
Differential 500X
(out)
Measurement instrument
displays or indicates the line
voltage
50X
(in)
Overrange indicator lights if
the input is 150 Vp
Hot (same
connection)
Common
Mode
50X or 500X No signal
This completes the functional chec k procedure.