Emerson Process Management 00809-0100-4952 Rev BA Stud Sensor User Manual


 
4
Reference Manual
00809-0100-4952, Rev BA
Section 2: Installation
February 2014
Installation
2.2 Installation flowchart and checklist
Figure 2-1 is an installation flowchart that provides guidance through the installation process.
Following the figure, an installation checklist has been provided to verify that all critical steps
have been taken in the installation process. The checklist numbers are indicated in the
flowchart.
Figure 2-1. Installation Chart
Start.
Unpack Instrument
Review Product Manual.
Verify proper installation location.
Steps 1, 2
Bench
Configure?
YES
See Appropriate Transmitter Manual for
Bench Configuration information.
NO
Verify model
indicated on tag.
Remote
Mounted
Transmitter?
NO
Finish
Install hardware
Install Transmitter
Install Pipe Clamp Sensor
Wire Sensor
Remote
Mounted
Transmitter?
YES
Commission the transmitter. See Appropriate
Transmitter Manual for Bench Configuration
information.
YES
NO
Steps 5-7
Steps 4
Steps 5-7
Steps 8-10