Southbend SB1023 Grinder User Manual


 
For Machines Mfg. Since 8/09 Model SB1023
-9-
PREPARATION
PREPARATION
Preparation Overview
The purpose of the preparation section is to help
you prepare your machine for operation.
The typical preparation process is as follows:
1. Unpack the machine and inventory the
contents of the box/crate.
2. Clean the machine and its components.
3. Identify an acceptable location for the
machine and move it to that location.
4. Level the machine and either bolt it to the
floor or place it on mounts.
5. Assemble the loose components and make
any necessary adjustments or inspections to
ensure the machine is ready for operation.
6. Connect the machine to the power source.
7. Test run the machine to make sure it
functions properly and is ready for operation.
Things You'll Need
During the setup process, operation, and
maintenance of your machine, you'll need the
following items:
For Lifting
• Aforkliftorotherpowerliftingdevice
rated for the weight of the machine.
• LiftingStrap or Chain (rated for at least
1500 lbs.)
For Power Connection
• Amachinepowerconnectionthatmeets
federal, state, and local electrical codes.
An electrician may be required.
For Assembly
• Assistant
• Cotton Rags
• Mineral Spirits
• SafetyGlasses
• Wrench 14mm
• Wrench 19mm
• Oil Can with any General Machine Oil