PR95 Operator’s Manual Prepare - 35
Prepare Jobsite
CMW
Dig Launch and Burster Pits
Dimensions
Requirements
Exit Pit (1)
• Must be in line with existing pipe.
• Sloped back end aids new pipe entry.
Burster Pit (2)
• Must be in line with existing pipe.
• Must allow burster to be level with existing pipe.
Unit Burster Pit Exit Pit *
Length (A) Width (B) Length (C) Width (D)
U.S. (metric) U.S. (metric) U.S. (metric) U.S. (metric)
PR95 12’ (3.6 m) 5’ (1.5 m) 10’ (3 m) 3’ (1 m)
* Exit pit dimensions depend on pipe depth and product being installed.