PR95 Operator’s Manual Burst Pipe - 49
Pull Pipe
CMW
8. Thread one rod onto rod in bursting unit.
9. Remove rod makeup device.
10. Push bursting unit back slightly to remove pulling brace.
11. Move burster back in pit and position extension frame between between pipe burster and existing pipe.
12. Put bursting unit in pull mode and pull towing system into extension frame.
13. Remove extension frame.
14. Disconnect and remove towing system.
15. Remove bursting unit from pit.
16. Connect both ends of new pipe to existing pipe to complete job.
IMPORTANT: Ensure extension frame is level and centered. Pull bursting unit forward until it is
firmly against extension frame.