Installation procedure
Fig 2
AE182FCAHA
AE092FCAHA
Installation of indoor unit
lThe unit shall be installed according to the
specifications to resist to strong wind and
earthquake. Improper installation may cause
dangers of unit falling down etc.
After selecting the unit installation location, proceed the following steps:
1. Drill a hole in the wall and insert the connecting pipe and wire through a PVC wall-through tube
purchased locally. The wall hole shall be with a outward down slope of at least 1/100. (See
Figure 2)
2. Before drilling check that there is no pipe or reinforcing bar just behind the drilling position.
Drilling shall avoid at positions with electric wire or pipe.
3. Mount the unit on a strong and horizontal building roof. If the base is not firm, it will cause
noise, vibration or leakage (see Figure 6).
4. Support the unit firmly.
5. Change the form of the connection pipe, connection wire and drain pipe so that they can go
through the wall hole easily.
lThe unit shall be installed at locations enough
to support the unit. If not, the air conditioner
may fall down and cause personal injury.
Figure showing installation dimensions: (unit:mm)
21
! Warning