Heatcraft Refrigeration Products H-IM-72A Air Compressor User Manual


 
17
Leak Checking, Evacuation,
and Start-up
Warning: It is illegal to knowingly vent or discharge
any CFC’s and HCFC’s to the atmosphere. ALL
CFC’s and HCFC’s must be reclaimed or recycled.
Leak Check
1. To check the systems for leaks, leave all valves closed on
suction, liquid and hot gas manifolds. The unit is shipped
with a holding charge of dry nitrogen and should be leak
free. Build up the pressure in each circuit to a maximum
of 150 psig dry nitrogen and check each individual circuit.
2. After each circuit has been checked, open all valves to
allow the pressure into the unit assembly. Check to be
sure pressure is throughout the assembly. Check all
connections and accessories for leaks.
Evacuation
1. After the system is leak checked, connect a good high
vacuum pump with fresh oil to both the low and high side
evacuation valves. Connections between the pump and
evacuation valves should be made with copper tubing or
high vacuum hose having a diameter of at least 3/8”.
Evacuate the system to 1500 microns for the first
evacuation.
2. After each evacuation, the vacuum should be broken by
the introduction of refrigerant into the system. The
refrigerant should be passed through a drier when
breaking the vacuum until the pressure is brought up to 0
psig.
3. Between the first and second evacuation, the liquid filter
driers and suction filters should be installed in each
replaceable core shell.
4. A triple evacuation is recommended. The third and final
evacuation should achieve a value of 500 microns or less.
After this vacuum is reached, add as much refrigerant as
possible into the receiver. Now the system is ready to be
started.
Start-up
1. Set all pressure controls as recommended elsewhere in
this manual. Recheck all service valves and shut-off
valves to be sure they are open.
2. Check and be sure the condenser fan motors are running
in the correct rotation.
3. All evaporator fan motors should be checked for proper
rotation. The fans in low temperature boxes generally
have a fan delay for defrost purposes that keep the fans
from operating until the evaporator coil has reached a
certain temperature. It will be necessary to jump-out the
fan controls on freezer units to make them run through
final charging and room temperature pull-down. The
wiring diagram for the unit will have to be consulted to
determine how to best force the fans to operate for this
step.
4. With all compressor and control breakers and toggle
switches turned off, apply power to the unit. If the unit is
using a phase monitor, the green light must come on
before going any further. (See instructions for phase
protector elsewhere in this manual.) A red light indicates
incorrect phasing or voltage. Check with a volt meter to
see if correct voltage is connected to the unit. Correct the
Power Supply before proceeding.
5. Turn on the circuit breaker for the control power. If an
electronic control system is installed on the unit, it will
initiate at this time. The Heatcraft preferred controller is
manufactured by Computer Process Control (CPC).
Review the manual for the controller supplied with the
system.
6. Turn on circuit breakers to all compressors. The
compressors can be started by turning on the compressor
toggle switches. Likewise, each circuit control can be
started by turning on the circuit toggle switch. It is
recommended that one compressor at a time be started
and checked before allowing them all to operate. It is also
advisable to check one circuit at a time to be certain all
components work when called upon and that the circuit
wiring is correct.
7. When each circuit and compressor has been tested and
the appropriate amount of refrigerant has been added for
proper operation, allow the system to operate and pull-
down the room/fixture temperatures.
8. Once the system is operating, set all regulating valves.
9. When the room and/or the fixture temperatures are at
design, the expansion valves should be set. (See
instructions elsewhere in this manual.)
10.Adjust the electronic or manual pressure controls as
necessary to maintain proper pressures and
temperatures.
11.Check the refrigerant level in the receiver. The minimum
level that should be maintained is 20%.
12.All circuit defrost controls must be set and checked.
Again, one circuit at a time should be tested.
13.Set condenser fan controls to maintain the proper
discharge pressure.
14.All safety controls should be checked and verified. Check
that the alarm circuitry is operating at this time.
15.Check the oil reservoir during the start-up and add oil as
necessary. The oil level should be between the upper and
lower reservoir sight glass. Do not add more than two
gallons of oil to a system. If more oil is needed, recheck
the piping as oil is not returning to the unit properly.