Wagner SprayTech GM 5000EAC Paint Sprayer User Manual


 
28
GM 5000EAC.
OPERATING MANUAL
EDITION 03/2012 PART NUMBER DOC 2319150
5.3 START-UP
5.3.1 GENERAL RULES FOR MAKING ADJUSTMENTS TO THE SPRAY GUN
Observe safety instructions in Chapter 2.
5.3.2 PREPARATION FOR STARTING UP
The following points should be noted before commissioning:
For earthing see paragraph 5.1.5; make sure that all other conductive parts within the
work area are earthed.
Connect the material hose to spray gun and material pump..
Check that all material-conveying connections are correctly connected.
Connect air hose to spray gun and to oil-free, dry air, approx. 0.25 MPa; 2.5 bar; 36 psi.
Compressed air quality class 3.5.2 according to ISO 8573.1.
Check that all air supply connections are connected properly.
Connect the electric cable to the spray gun and to the VM 5000 or VM 500 control
unit.
Visually check the permissible pressures for all the system components.
DANGER
High voltage field!
Danger to life from malfunctioning heart pacemakers
Ensure that persons with heart pacemakers:
Do not work with the electrostatic spray gun.
 Remain outside the area of the electrostatic spray gun/work -
piece.
SIHI_0049_GB
SIHI_0065_GB
WARNING
Unintentional putting into operation!
Risk of injury
Before all work on the unit, in the event of work interruptions and
functional faults:
Switch off the energy/compressed air supply.
Relieve the pressure from the spray gun and unit.
Secure the spray gun against actuation.
By functional faults: Identify and correct the problem, proceed
as described in chap „Trouble shooting“.