Baum Bros. Imports 26.4 Saw User Manual


 
K1 - 4
Transport and Installation of the Machine
1.0 Technical Data/Machine Layout/Transport and Installation of the Machine/Safety Relevant Machine Elements
Have the machine installed by BAUM service personnel, exclusively!
The installation of the machine requires special skills which can be
guaranteed only by especially trained experts of BAUM agencies.
Arbitrary working on the machine may damage the machine itself or other
material property of the user or cause accident endangering life and limb
of the staff.
The machine must be unpacked, moved, transferred and installed by
authorized BAUM Service Technicians only. Dangers might arise from the
machine itself or from its packing if it is unpacked, moved, transferred or
installed with unsuitable devices.
While the machine is unpacked, moved, transferred and installed, no
other persons must be present in the range of the machine or its packing.
The BAUM Service Technician must also take care that no unauthorized
persons work at the machine, its packing or the installation equipment.
After Unloading
Remove all packing and wrapping material
Check machine and accessories for damages
Check for missing parts
In Case of Complaints
Immediately send written note to:
Railway or shipping company
Insurance company
BAUM / Agency
Place of Installation
The location must meet the following requirements:
Vibration free location
Even concrete flooring, concrete property class min. (N/mm²) according to
eurocode 2: C20/25 or according to DIN1045: B 25.
Observe carrying capacity!
Avoid possible accidents of operator by uneven flooring
Adhere to minimum distance from buildings or peripheral equipment (see
plan)
After the Installation of the Machine
1. Remove anti rust paint (agent: kerosene, gasoline) from the machine on
the site of installation
Note:
Do not use any sharp tools to remove anti-rust paint!
2. Clean plastic covers only with plastic cleansing agent
3. Final check according to check list
4. Have handover signed