3. Remove the front cover from the bottom cabinet to access the
front shipping bracket.
Press and release the handle latch at the bottom of the cover and
then lift the cover up and off the cabinet.
4. Remove the three M10 bolts securing the rear shipping pad to the
pallet and remove the shipping pad (see Figure 3).
NOTE Hold the back of the cabinet so that the bolts can be removed easily without the
cabinet rolling backward.
5. Remove the two M10 bolts securing the front shipping bracket and
remove the bracket.
If needed, adjust the leveling feet to release the bracket.
Stabilizing Bracket
Front Shipping
Bracket
Shipping Pad
M4 Screws
M10 Bolts
M10 Bolts
Figure 3. Removing the Brackets and Shipping Pad
6. Reinstall the front cover removed in Step 3.
Hang the top edge of the cover on the cabinet first, then lower the