Powerware 9155 Tool Storage User Manual


 
OPERATION
EATON Powerware
®
9155 Parallel UPS (8–15 kVA) User’s Guide S 164201592 Rev C www.powerware.com
46
6. Configure the UPS for parallel operation through the front panel:
S Press any button on the front panel display to activate the menu
options.
S Using the button, scroll to the Settings menu, and then press
the
button twice to select the User Settings menu.
S Using the button, scroll to the Parallel Operation Settings
option and press the
button.
S Press the button to select the Parallel Unit Number option.
S Use the button to scroll the Unit number to identify the UPS
number of the parallel system (Unit #1, Unit #2, or Unit #3).
S Press the button to save the setting.
S Use the button to scroll to the Parallel Operation Mode option
and press the
button to enter the menu.
S Use the button to scroll the desired option (either Redundant
Mode or Capacity Mode).
S Press the button to save the setting.
7. Press the
ESC
button until the Eaton Powerware logo appears.
8. Repeat Steps 6 and 7 for the remaining UPSs in the parallel system.