York YR Air Compressor User Manual


 
16
YORK INTERNATIONAL
FORM 160.81-EG1
Mechanical Specifications (continued)
11. A numbered terminal strip for all required field in-
terlock wiring.
12. An RS-232 port to output all system operating data,
shutdown / cycling message, and a record of the
last 10 cycling or safety shutdowns to a field-sup-
plied printer. Data logs to a printer at a set pro-
grammable interval. This data can be
preprogrammed to print from 1 minute to 1 day.
13. The capability to interface with a building automa-
tion system to provide:
a. remote chiller start and stop
b. remote leaving chiller liquid temperature adjust
c. remote current limit setpoint adjust
d. remote ready to start contacts
e. safety shutdown contacts
f. cycling shutdown contacts
g. run contacts
STARTUP AND OPERATOR TRAINING
The services of a factory-trained, field service repre-
sentative will be provided to supervise the initial startup
and conduct concurrent operator instruction.
CODES AND STANDARDS
ASME Boiler and Pressure Vessel Code Section
Vlll Division 1.
ARI Standard 550/590
c/U.L. Underwriters Laboratory
ASHRAE 15 Safety Code for Mechanical Refrig-
eration
ASHRAE Guideline 3 – Reducing Emission of Ha-
logenated Refrigerants in Refrigeration and Air-Con-
ditioning Equipment and Systems
NEC National Electrical Code
OSHA Occupational Safety and Health Act
ISOLATION MOUNTING
The unit is provided with four vibration isolation mounts
consisting of 1" (25.4 mm) thick neoprene isolation pads
for field mounting under the steel mounting pads lo-
cated on the tube sheets.
REFRIGERANT CONTAINMENT
The standard unit has been designed as a complete
and compact factory packaged chiller. As such, it has
minimum joints from which refrigerant can leak. The
entire assembly has been thoroughly leak tested at
the factory prior to shipment. The YORK chiller in-
cludes service valves conveniently located to facili-
tate transfer of refrigerant to a remote refrigerant stor-
age/recycling system. Optional condenser isolation
valves permit storage of the charge in the condenser.
PAINT
Exterior surfaces are protected with one coat of Carib-
bean blue, durable alkyd-modified, vinyl enamel, ma-
chinery paint.
SHIPMENT
The unit shall be completely assembled, with all main,
auxiliary, and control piping installed, controls wired,
leak tests completed, functional run tests completed,
and refrigerant charge in place. The oil charge, relief
device and other miscellaneous materials shall be
packed separately.
Protective covering is furnished on the Control Center
and unit-mounted controls. The entire unit is then shrink-
wrapped with high-quality reinforced plastic to provide
maximum protection during transit. Water nozzles are
capped with fitted plastic enclosures.