Teledyne 7600 Welding Consumables User Manual


 
Infrared Gas Analyzer Installation
Teledyne Analytical Instruments 21
Installation
Installation of the analyzer includes:
1. Unpacking the system.
2. Choosing a suitable location
3. Mounting the analyzer
4. Mounting the terminal module
5. Installing gas connections
6. Making electrical connections
7. Testing the installation.
CAUTION: READ THIS CHAPTER IN ITS ENTIRETY BEFORE
INSTALLING THE SYSTEM.
FOR INDOOR USE ONLY.
2.1 Unpacking the Analyzer
The Model 7600 Infrared Gas Analyzer is shipped with the
following components:
7600 Analyzer
Input/Output terminal module set
Connection cable
Power cable
Fuse (2)
Cell window mounting tool
Slide rail (2)*
Relay board for auto calibration*
Relay board connection cable*
Instruction manual