Emerson Process Management BINOS 100 F OXYNOS 100 Welding Consumables User Manual


 
24 - 5
REPLACEMENT AND CLEANING OF PHOTOMETRIC COMPONENTS
ETC00781(4) Series 100 e 02/2004
24.3.3 Reinstalling the Analysis Cells
a) For analysis cells of lengths 1 mm and 7 mm
P Place the O-rings on the adapter cell and filter cell.
P Fit the components together.
P Install the clamping collars with the clamp and tighten it.
b) Analysis cells of lengths 50 mm - 200 mm:
P Place the O-ring on the chopper housing side of the cell body.
P Position the cell body in place and fasten it using the two mounting screws
(Fig. 24-2, Item 4).
P Place the O-ring on the filter cell.
P Fit the filter cell on the cell body.
P Install the clamp and tighten.
Only analyzer with gas detector:
P Assembly preamplifier to analysis cell
Then:
P Reinstall the photometer assembly (see chapter 24.5).
REINSTALLING OF ANALYSIS CELLS