Super Finish 27 • 31
31
GB
Starting operation
Pay attention to the fact that the red inlet (2) is inserted into
the coating material inlet.
Screw the upper hopper (3) onto the coating material inlet 3.
(4).
Hang the return pipe (5) into the upper hopper.4.
Screw the union nut (6) on the return pipe (5) onto the
5.
connection (7).
3
5
4
3
2
5
6
7
4
1
Screw the high-pressure hose (g. 8, item 1) onto the hose 1.
connection (2).
Screw the spray gun (3) with selected tip onto the high-
2.
pressure hose.
Tighten the union nut on high-pressure hose so that no
3.
coating material escapes.
3
5
4
3
1
2
4.4
Attention
The connection must take place through a
correctly earthed two-pole and-earth socket
outlet.
Before connection to the mains, pay attention to the fact
that the mains voltage agrees with the information on
the makers’ name plate on the rear of the unit.
The green control lamp will light up as soon as the mains plug
has been connected.
4.5
Submerge suction pipe into a vessel lled with a suitable
cleaning agent
2.
Fill suitable cleaning agent into the upper hopper.
Set multifunction switch (g. 9, item 1) to
3.
(ON–
circulation); the unit commences to run. Turn pressure
regulation knob (2) to the right until stop.
Wait until the cleaning agent ows out at the re-turn pipe.4.
Set multifunction switch (1) to
5.
(spray). Pull trigger guard
of spray gun.
Spray cleaning agent from the unit into an open collection 6.
container.
3
5
4
2
1
Turn pressure regulating knob (g. 10, item 1)
1.
three
revolutions to the left.
Set multifunction switch (2) to
2.
(ON – circulation). The
hydraulic system is ventilated. Leave the unit on for two to
three minutes.
Then turn the pressure regulating knob (1) to the
3.
right until
stop. Sound of the inlet valve is audible.
If not, repeat points 1 and 3. 4.