Fuji Labs ZSP Welding Consumables User Manual


 
5
5. DESCRIPTION OF EACH PART
Please refer to Chapter 14 specification attached at the end of the manual.
6. PREPARATION FOR OPERATION
6.1 Injection of clean water
Inject clean water through the filter or air aspiration port until it overflows from the gas conditioner.
6.2 Supply of external power
Supply external power to the analyzer. And check the connections with output signal wire, etc. The exter-
nal power supply should be.........
100V±10% AC,
50/60 Hz ±1%,
with power consumption of 0.9kVA max. (excluding heating pipe).
Check with reference to the separately issued approval diagrams.
6.3 Check of sample piping, exhaust piping, etc.
Check the connection of the sample piping and if necessary, provide exhaust piping + drain piping (Pipes
with inner diameter of ø8 or more for both). When sample will be dispersed upward, then branch and water-
seal the exhaust pipe for the purpose of drain separation. Be sure to disperse the exhaust into the atmo-
sphere.
Make checks with reference to the piping instructions in Fig. 4-1 and the separately issued gas analyzer
diagram.