Honeywell NXL Welding System User Manual


 
84(96) Commissioning
Honeywell
HoneywellHoneywell
Honeywell
8
9
Run the start-up tests without the motor being connected to the process, if possible. If this is not
possible, secure the safety of each test prior to running it. Inform your co-workers of the tests.
a)
Switch off the supply voltage and wait up until the drive has stopped as advised at Chapter 8.1,
step 5.
b)
Connect the motor cable to the motor and to the motor cable terminals of the frequency converter.
c)
See to that all Start/Stop switches are in Stop positions.
d)
Switch the mains ON
e)
Repeat test 8A or 8B.
10
Connect the motor to the process (if the start-up test was run without the motor being connected)
a)
Before running the tests, make sure that this can be done safely.
b)
Inform your co-workers of the tests.
c)
Repeat test 8A or 8B.