APC 412 kVA Battery Charger User Manual


 
CHAPTER 4: INSTALLATION
25
Completing the Installation
1. Install all power modules. Power modules
can be installed in any slot on the left side of
the UPS.
Slide the power module into the frame.
Slide the latch up and tighten the
captive screw .
Two people are required to lift,
move, install, or remove battery
modules due to its weight.
Do not install battery modules
until you are ready to power up
the UPS. Batteries can be
permanently damaged if loaded
prematurely.
2. Install all battery modules on the right side of
the UPS.
Slide the battery module into the frame
until the safety latch
engages.
Slide the latch up and tighten the
captive screw
.