Site Planning Considerations
This chapter describes the general considerations to address while planning for the installation of the
Cisco
CRS-1 8-Slot Line Card Chassis. It does not repeat the specifications in Chapter 3, but you should
keep those specifications in mind as you plan for your system.
This chapter includes the following sections:
Basic Site and Installation Planning
Tools Required for Installation
Equipment Rack Considerations
Aisle Spacing and Maintenance Access Floor Plan
Power and Cooling Requirements
System Console
Cable Management
Route Processor Cables
PLIM Interface Cables
Custom Cables
Noise Control
Cisco Installation Services
System Testing, Certification, and Warranties
Basic Site and Installation Planning
As you plan for basic site and installation requirements, consider the following:
Does the installation site have adequate power for the routing system?
Can the routing system be positioned close to the AC or DC power source, and are the power
receptacles easy to reach?
Does the site have appropriate equipment racks with space available in which to install the system?
Are additional equipment racks required? See the
“Equipment Rack Specifications” section on
page 3-2 for information about rack requirements.
Is there a scissor lift or similar lifting device available to lift the chassis into the equipment rack?
In addition, make sure that the installation site meets the following access requirements: