Dell SCv2020 Tool Storage User Manual


 
Connect Power Cables and Turn on the Storage System
Connect power cables to the storage system components and turn on the hardware.
About this task
If the storage system is installed without expansion enclosures, connect power cables to the storage
system chassis and turn on the storage system.
If the storage system is installed with expansion enclosures, connect power cables to the expansion
enclosure chassis and turn on the expansion enclosures as described in the Dell Storage Center
SC100/SC120 Expansion Enclosure Getting Started Guide. After the expansion enclosures are
powered on, connect power to the storage system chassis and turn on the storage system.
Steps
1. Ensure that the power switches are in the OFF position before connecting the power cables.
2. Connect the power cables to both power supply/cooling fan modules in the storage system chassis
and secure the power cables firmly to the brackets using the straps provided.
Figure 63. Connect the Power Cables
3. Plug the other end of the power cables into a grounded electrical outlet or a separate power source
such as an uninterrupted power supply (UPS) or a power distribution unit (PDU).
4. Press both power switches on the rear of the storage system chassis to turn on the storage system.
Figure 64. Turn on the Storage System
When the SCv2000/SCv2020 storage system is powered on, there is a delay while the storage
system prepares to start up. During the first minute, the only indication that the storage system is
72