Dell SCv2020 Tool Storage User Manual


 
Test Basic Connectivity
Verify basic connectivity by copying data to the test volumes.
1. Connect to the server to which the volumes are mapped.
2. Create a folder on the TestVol1 volume, copy at least 2 GB of data to the folder, and verify that the
data copied successfully.
3. Create a folder on the TestVol2 volume, copy at least 2 GB of data to the folder, and verify that the
data copied successfully
Test Storage Controller Failover
Test the Storage Center to make sure that a storage controller failover does not interrupt IO.
1. Connect to the server, create a Test folder on the server, and copy at least 2 GB of data into it.
2. Restart the top storage controller while copying data to verify that the failover event does not
interrupt IO.
a. Copy the Test folder to the TestVol1 volume.
b. During the copy process, restart the top storage controller (the storage controller through which
TestVol1 is mapped) by selecting it from the Hardware tab and clicking Shutdown/Restart
Controller.
c. Verify that the copy process continues while the storage controller restarts.
d. Wait several minutes and verify that the storage controller has finished restarting.
3. Restart the bottom storage controller while copying data to verify that the failover event does not
interrupt IO.
a. Copy the Test folder to the TestVol2 volume.
b. During the copy process, restart the bottom storage controller (the storage controller through
which the TestVol2 is mapped) by selecting it from the Hardware tab and clicking Shutdown/
Restart Controller.
c. Verify that the copy process continues while the storage controller restarts.
d. Wait several minutes and verify that the storage controller has finished restarting.
Test MPIO
Perform the following tests for a Storage Center with Fibre Channel or iSCSI front-end connectivity if the
network environment and servers are configured for MPIO. Always perform the following tests for a
Storage Center with SAS front-end connectivity.
1. Create a Test folder on the server and copy at least 2GB of data into it.
2. Make sure that the server is configured to use load balancing MPIO (round-robin).
3. Manually disconnect a path while copying data to TestVol1 to verify that MPIO is functioning
correctly.
a. Copy the Test folder to the TestVol1 volume.
b. During the copy process, disconnect one of the paths and verify that the copy process continues.
c. Reconnect the path.
4. Repeat the previous steps as necessary to test additional paths.
5. Restart the storage controller that contains the active path while IO is being transferred and verify
that the IO process continues.
6. If the front-end connectivity of the Storage Center is Fibre Channel or iSCSI and the Storage Center
is not in a production environment, restart the switch that contains the active path while IO is being
transferred, and verify that the IO process continues.
Perform Post-Setup Tasks
87