This portion of the manual discusses initial installation for the RUSKA 7350. Installing
the RUSKA 7350 is a relatively simple process of unpacking the RUSKA 7350,
powering it up, and then using the front panel to configure the system.
Unpacking the RUSKA 7350
Carefully unpack all components, checking for obvious signs of damage. In addition to
any nonstandard items ordered with the RUSKA 7350, the shipment should contain at
least the following items:
RUSKA 7350
power cord, and this user’s manual
grease gun and grease
If necessary, report any shipping damage to the freight agency. Remove masking tape,
strings, and packing materials from all components. If possible, save the packing
materials for future use.
Finally, install the Calibrator in a location that meets the requirements listed in Table 3-1.
Note
The RUSKA 7350 should not be subjected to mechanical shocks during
installation or use. It should be mounted on a rigid bench or in a sturdy
19 inch rack. Although the zeroing process will compensate for a slightly
unlevel mounting; the RUSKA 7350 should be mounted to within 5º of level.
Table 3-1. General Specification and Parameters
Parameter Value Model
Operating Humidity Range 5% to 95% RH all
Operating Temperature Range 5 °C to 50 °C all
Storage Humidity Range None
1
all
Storage Temperature -20 °C to 70°C all
Power Requirements 100 – 120 VAC or 220 – 240 VAC all
Warm Up Period 30 minutes all