POWER MIG 255
TROUBLESHOOTING & REPAIR
F-52 F-52
Return to Section TOC Return to Section TOC Return to Section TOC Return to Section TOC
Return to Master TOC Return to Master TOC Return to Master TOC Return to Master TOC
6. Remove the two transformer secondary
leads X2 and X3 (braided copper strap)
from the negative capacitor bank buss
bar using two 1/2 in. open end wrench-
es.
7. Disconnect and label all transformer
leads from the reconnect panel using a
3/8 in. open end wrench.
8. Disconnect and label all leads from the
input power switch.
9. Remove the power switch.
10. Disconnect thermostat leads #320 and
#320B from the SCR Rectifier.
PROCEDURE
1. Disconnect main input power to the
machine.
2. Remove the case side panels using a
3/8 in. nutdriver.
3. Test that the capacitors are discharged
using a volt ohmmeter. Polarity must
be observed.
4. Remove lead X1 from the left side SCR
heat sink assembly using a 1/2 in. sock-
et wrench, extender and universal
adapter. See Figure F.17.
5. Remove lead X4 from the right side
heat sink assembly using a 1/2 in. sock-
et wrench, extender and universal
adapter.
FIGURE F.17 — MAIN TRANSFORMER REMOVAL.
OUTPUT
CHOKE
LEAD
LEAD
X1
LEAD
X4
LEADS
X2 AND X3
POWER
ENHANCEMENT
CHOKE
MAIN
TRANSFORMER
PLUG-IN LEADS ARE
NOT SHOWN FOR
CLARITY.
NOTE:
OUTPUT
CHOKE
POSITIVE
LEAD
MAIN TRANSFORMER AND OUTPUT CHOKE
REMOVAL AND REPLACEMENT (continued)