Setup
Trailer Setup
Guidelines
Route exhaust system away from combustible
materials to prevent materials from igniting or gas
recirculation into a wall, ceiling, or a concealed
space. Provide exhaust system guards to prevent
burns.
NOTICE
Provide recommended size louvers. Failure to do
so can damage the engine and void the engine
warranty.
Exhaust pipes that pass through flammable ceilings
must be guarded by vented metal thimbles that
extend at least 9 in. (228.6 mm) below and above
the roof and are at least 6 in. (152.4 mm) in diameter
larger than the exhaust pipe.
Exhaust pipes that pass through flammable walls
must be guarded by either:
• Metal ventilated thimble at least 12 in. (305 mm)
larger than the diameter of the exhaust pipe.
• Metal or other approved fireproofing materials
that provides at least 8 in. (203 mm) of insulation
between the exhaust pipe and flammable material.
Exhaust pipes not covered above must have at least
9 in. (228.6 mm) of clearance from the outside of the
exhaust pipe to adjacent flammable materials.
1. Provide sufficient lighting to safely operate and
maintain system equipment.
2. Provide radiator exhaust for Reactor. Use a 400
in.
2
(258,064 mm
2
) minimum louver.
3. Provide air duct to connect radiator exhaust to
louver.
4. Provide a 400 in.
2
( 258,064 mm
2
) minimum fresh
air intake louver near the generator.
5. Remove red exhaust cap.
6. Provide a minimum 2 in. (50.8 mm) diameter
engine exhaust outlet with flexible pipe element.
Provide rain cap, or equivalent routing, to prevent
moisture from entering the metal exhaust pipe.
Radiator Exhaust and Air Intake Louvers
Figure 25
3A1705J 35