Pre Start-Up Checklists
The following checklists are to help prepare the equipment before the Vilter Technician arrives at the
jobsite. Vilter recommends that a Trained Technician go through the following tasks. The operating
Manuals provided by Vilter, can be referenced for any type of questions or special instructions.
Every Refrigeration unit includes a Vilter Start-Up (Conrm on PO). The following tasks are not included
in the Vilter Start-up provided in your equipment purchase. Any tasks below that are done by the Vilter
Technician will take away from the pre-determined time that was provided with the equipment pur-
chase. Vilter suggests that the Vilter Technician’s time be used during the start-up of the System and
not for the below System Preparation.
Note: Each item below MUST be “Checked-Off”, Signed and Returned to the Vilter Service Department.
Failure to do so will “Null & Void” future Warranty considerations.