Conair UGR003/0800 Welding System User Manual


 
UGR003/0900 UCR-150L Robot
MAINTENANCE 5-5
P
REVENTATIVE
MAINTENANCE
SCHEDULE
Checking angle of rotation
Check for correct angle of rotation of the arm. Adjust
as necessary.
Checking timer settings
Check that settings have not changed. Adjust as need-
ed.
Verifying sequence
Check that robot is performing the correct sequences.
Correct as needed.
Monthly
Inspecting the filter regulator
Check that the filter regulator is set at the correct pres-
sure. Check the filter and clean or replace it as needed.
Checking the solenoid valves
Check that the solenoid valves are working properly.
Replace as needed.
Inspecting the gripper for wear
Check the gripper fingers for wear. Replace as needed.
Checking the exhaust filter
Check the filter and clean or replace it as needed.
Examining the suction cups
Inspect the suction cups and replace if worn or dam-
aged.
Inspecting electrical terminals
Check all electrical terminals for tightness; adjust as
needed. See Checking Electrical Connections, in the
Maintenance section.
Checking all electrical cables
Inspect all electrical cables for cuts and abrasions.
Replace as needed.
Inspecting hand pendant display
Check to make sure no LCD display is functioning
correctly. Replace as needed.