Hitachi CONVENTION 14 Welding System User Manual


 
Ensure Adequate Ventilation
Step 2: To summarize the caution messages – you will need to find a solid, non-
flammable, vertical surface that is in a relatively clean and dry environment. In order to
ensure enough room for air circulation around the inverter to aid in cooling, maintain
the specified clearance and the inverter specified in the diagram.
C
AUTION: Be sure to maintain the specified clearance area around the inverter and to
provide adequate ventilation. Otherwise, the inverter may overheat and cause
equipment damage or fire.
Keep Debris Out of Inverter Vents
Step 3: Before proceeding to the wiring section, it’s
a good time to
temporarily
covers the inverter’s
ventilation openings. Paper and masking tape are
all that is needed. This will prevent harmful debris
such as wire clippings and metal shavings from
entering the inverter during installation.
Please observe this checklist while mounting the
inverter:
1. The ambient temperature must be in the range
of 10 to 40qC.
2. Keep any other heat-producing equipment as
far away from the inverter as possible.
3. When installing the inverter in an enclosure, maintain the clearance around the
inverter and verify that its ambient is within specification when the enclosure door
is closed.
4. Do not remove the front housing at any time during operation.
2
3
210
Inverter Mounting
and installation
Ventilation holes
(top)
Ventilation holes
(both sides)
A
ir flow
10 cm (3.94”)
minimum
10 cm (3.94”)
minimum
5 cm (1.97”)
minimum
5 cm (1.97”)
minimum
Clear area
X200
inverter
2 10
Inverter Mountingand
installation