Topcon A2677 Paint Sprayer User Manual


 
8-26
www.topconpa.com
X20 Sprayer Reference Manual
15 Boom Sections using 2 wire section valves with a 2 wire
dump valve fitted.
If Dual is selected the Spray Interface can control 3 primary
sections valves and 3 secondary sections valves, giving a total of 6
sections.
If Dual is selected and Spray ECU (see page 8-7) is selected, then
the system can operate up to:
15 Boom Sections on the primary and 15 Boom Sections on
the secondary line, using 3 wire section valves or solenoids
with a 3 wire dump valve fitted
7 Boom Sections on the primary line and 7 Boom Sections
on the secondary line using 2 wire section valves with a 2
wire dump valve fitted
8 Boom Sections on the primary line and 8 Boom Sections
on the secondary line and no Dump Valve fitted.
Sections
Set the number of sections by pressing the calculator icon. See
Appendix A for help with using the calculator icon.
Enter the number of section valves on the primary line.
Setting the Number of Sections When Selecting
Dual
If Dual was selected and, for example there are 8 sections on the
primary line and 8 sections on the secondary line, then ‘8’ would
be entered as the number of sections.
See page 8-49 to set the Low Speed Shutoffs for the primary line
(section valves 1-8) and the secondary line (section valves 9-16).